NEWS
ITEMS
TO: Mayor
and Council
FROM: Jean
DATE: June
8, 2012
1.
VISION IOWA:
The city received the grant agreement this week and will have 45 days to
return required paperwork. I am working on finalizing agreements with all the
relevant groups.
2.
WELLNESS
CENTER: Jeff Larson, Larson & Larson Construction indicates work on the
wellness center will commence June 11th.
3.
DUST
CONTROL: 26 residents participated in the dust control program. The city
pays 50% for a calcium chloride application for those that live on gravel roads
within the city limits. The city’s portion was approximately $3,400.
4.
POOL: Glen
reports there are issues with the pool slide installation and the dept is
working with Global Specialty (contractor) to get resolved. We have paid them
less than half of the contract amount and will hold any additional payments at
this time.
5.
WCEDC: I
am asking John Hoyman to review the draft agreement developed by staff and will
forward to you as soon as received.
6.
STREET
PROJECT: The
sanitary sewer services are being completed along the North/South D Street
corridor. The West 1/2 of South Buxton has been completed. We anticipate the
remaining portion to be complete the week of June 11th. North E Street subgrade
prep revealed a gas main conflict. We are working through the issue and hope to
have it resolved by early next week. The conflict may prevent the street from
being completed prior to the Opera season.